6.1 Introduction
6.2 Starting PACE
6.3 Machine Rate Calculations
6.4 Road Construction Calculations
6.5 Production and Unit Cost
6.6 Sensitivity Analysis
6.7 Installing the PACE Program
6.2 Starting PACE
6.3 Machine Rate Calculations
6.4 Road Construction Calculations
6.5 Production and Unit Cost
6.6 Sensitivity Analysis
6.7 Installing the PACE Program
6.1 Introduction
The computer program, PACE (Production and Cost
Evaluation), was developed to assist in calculating machine rates, road
construction costs, and harvesting costs. It can be used to evaluate tradeoffs
between road costs and harvesting costs. This section will describe the PACE
program and can be used as a user guide. A computer disk with the PACE program
for IBM PC/XT/AT and compatibles are provided with this manual. See Section 6.7
for installation instructions.
PACE is divided into three parts: (1) machine
rate calculations, (2) road construction calculations, and (3) harvesting
production and unit cost calculations. Analysis begins with the preparation of
machine rates for combinations of equipment and labor which will be used in
road construction and harvesting. Next, road construction costs are developed
using the machine rates from (1). And last, machine rates, road costs, and
harvesting production rates are combined to develop production and unit cost
estimates (Figure 6.1).
Figure 6.1 Information
flow for PACE program.
PACE is easily learned through a tutorial
example. The tutorial includes calculation of a machine rate, a road
construction cost, and a harvesting production and cost estimate Copies of the
computer monitor displays are included along with the formulas used to make the
calculations.
6.2 Starting PACE
PACE consists of six programs linked together by
an executive program with the main menu. Type PACE and press <enter>. The
monitor will display the main menu (Figure 6.2). You are now ready to begin.
6.3 Machine Rate Calculations
Let's begin by preparing a machine rate for an
operator with a power saw. To reach the machine rate program menu (Figure 6.3),
use the cursor control arrows to highlight the machine rate program, MAC-COST.EXE
and press <enter>. The MAC-COST menu (Figure 6.3) will appear.
Follow the key strokes below to enter the data
and refer to the formulas in Table 6.1 to understand how PACE is making the
calculation.
Key
stroke
|
Explanation
|
1
|
Branches to equipment ownership
cost screen (Figure 6.4).
|
550
|
Type in 550 and either press
<enter> or press the down arrow key to enter the data and move to the
next line.
|
...
|
[continue with input as shown in
Figure 6.4]
|
<esc>
|
Returns to the main menu of the
machine cost program.
|
Table 6.1 Machine Rate
Ownership Cost Formulas
Row
|
Description
|
1
|
Delivered equipment cost
|
2
|
Line and rigging cost
|
3
|
Tire or track replacement cost
|
4
|
Residual value
|
5
|
Equipment life
|
6
|
Days equipment works per year
|
7
|
Hours equipment works per day
|
8
|
Interest rate
|
9
|
Blank
|
10
|
Tax, lic, insur, storage rate
|
11
|
Depreciable value
|
12
|
Annual depreciation
|
13
|
Average annual investment
|
14
|
Annual interest expense
|
15
|
Annual cost tax, lic, insur,
storage
|
16
|
Annual ownership cost
|
17
|
Annual hours utilization
|
18
|
Hourly ownership cost
|
Rows (1) - (10) are input data.
Row (11) = Row (1) - Row (4) Row (12) = Row (11) / Row (5) Row (13) = [Row (1) - Row (4)] [Row (5) +1] / [2 * Row (5)] + Row (4) Row (14) = Row (8) * Row (13) / 100 Row (15) = Row (10) * Row (13) / 100 Row (16) = Row (12) + Row (14) + Row (15) Row (17) = Row (6) * Row (7) Row (18) = Row (16) / Row (17) |
Key
stroke
|
Explanation
|
2
|
Selects the operating cost screen.
|
100
|
Enter the operating costs as shown
in Figure 6.5.
|
...
|
[continue with input as shown in
Figure 6.5]
|
<esc>
|
Returns to the main menu.
|
Table 6.2 Machine Rate
Operating Cost Formulas
Row
|
Description
|
1
|
Repairs as % of equip depreciation
|
2
|
Fuel consumption rate
|
3
|
Fuel cost
|
4
|
Lubricants as % of fuel
consumption
|
5
|
Cost of oil and lubricants
|
6
|
Cost of lines
|
7
|
Life of lines
|
8
|
Cost of rigging
|
9
|
Life of rigging
|
10
|
Cost of tires or tracks
|
11
|
Life of tires or tracks
|
12
|
Hourly cost of repairs and maint
|
13
|
Hourly cost of fuel
|
14
|
Hourly cost of oil and lubricants
|
15
|
Hourly cost of lines
|
16
|
Hourly cost of rigging
|
17
|
Hourly cost of tires or tracks
|
18
|
Hourly total operating cost
|
Rows (1) - (11) are input data.
Row (12) = Row (1) * Row (12)1 / Row (17)1 / 100 Row (13) = Row (2) / Row (3) Row (14) = Row (2) * Row (4) * Row (5) / 100 Row (15) = Row (6) / Row (7) Row (16) = Row (8) / Row (9) Row (17) = Row (10) / Row (11) Row (18) = Row (12) + Row (13) + Row (14) + Row (15) + Row (16) + Row (17)
------------------
1 Refers to row numbers and values from table 6.1.
|
Key
stroke
|
Explanation
|
3
|
Selects the labor cost screen.
|
1.10
|
Enter the labor costs as shown in
Figure 6.6
|
...
|
[continue with input as shown in
Figure 6.6]
|
<esc>
|
Returns to the main menu.
|
Table 6.3 Machine Rate
Labor Cost Formulas
Row
|
Description
|
1
|
Base wage for 1st crew position
|
2
|
Base wage for 2nd crew position
|
3
|
Base wage for 3rd crew position
|
4
|
Base wage for 4th crew position
|
5
|
Base wage for 5th crew position
|
6
|
Base wage for 6th crew position
|
7
|
Fringe benefits
|
8
|
Non-machine operating hours per
day
|
9
|
Machine operating hours per day
|
10
|
Supervision as % of direct labor
|
11
|
Total number of workers
|
12
|
Hourly crew wage
|
13
|
Hourly direct labor cost per
machine operating hour
|
14
|
Hourly supervision cost per
machine operating hour
|
15
|
Hourly total labor cost per
machine operating hour
|
16
|
Hourly operating cost (equip +
labor) per machine operating hour
|
Rows (1) - (10) are input data.
Row (11) = Sum of workers Row (12) = Row (1) + Row (2) + Row (3) + Row (4) + Row (5) + Row (6) Row (13) = Row (12) * [ 1 + Row (7) / 100 ] * [ Row (8) + Row (9) ] / Row (9) Row (14) = Row (13) * Row (10) / 100 Row (15) = Row (13) + Row (14) Row (16) = Row (15) + Row (18)1
------------------
1 Refers to Row (18) from Table 6.2.
|
Key
stroke
|
Explanation
|
4
|
Selects the summary cost screen.
This screen should appear as Figure 6.7.
|
Displays the summary of the
ownership, operating, and labor costs on the monitor. The equipment
description appears at the top of the summary sheet. This was added using
option 7 from Figure 6.3.
|
|
<esc>
|
Returns to main menu.
|
Key
stroke
|
Explanation
|
6
|
Selects the save-data option.
|
70CCSAW
|
Enter file name. Name must not be
more than 8 characters with no decimal point.
|
Stores the information from
screens 1, 2, 3, and 4 to the disk.
|
|
We have now completed all
information for the machine rate example. Let's try some other options.
|
|
5
|
Displays all machine rate files
which have been made with the MAC-COST program and stored on disk. This
option is used to recall files.
|
Note an extension .MAC has been
assigned by the program for use in later file manipulations.
|
|
To load a file, highlight the
desired file using the cursor control arrows and press <enter>. The
file will be loaded and the program returns to the main menu.
|
|
8
|
Erases the information currently
on the 1, 2, 3, and 4 screens.
|
9
|
Returns to the executive program.
(Figure 6.2)
|
This completes the machine cost file
preparation. Machine rates for trucks and animals are prepared similarly. The
logic is identical with only slightly different questions being asked which are
specific to the machine/labor combination being evaluated. Remember, the
machine rates are the basic building blocks of any cost analysis and should
represent the labor and cost combinations which you will use in later programs.
A machine rate could a machine without crew, a machine with crew or a crew
without machine. Typical applications might be a power saw with operator, a
tractor with operator and helpers, a survey crew with pickup, etc.
6.4 Road Construction Calculations
To prepare a road construction cost estimate for
a typical road section we use the CONST.EXE program. The objective of the Road
Construction Program (CONST.EXE) is to allow you to develop road construction
costs for typical sections of roads or typical road standards. The road costs
can then be used in the UNIT.EXE program to develop stump-to-mill harvesting
costs and to evaluate the sensitivity of harvesting costs to road spacing
alternatives. The CONST.EXE program allows you to specify which equipment/labor
combinations you will use for road construction and retrieves the files from
your disk. You then estimate the production rates for the equipment/labor
combinations for each road construction activity (Figure 6.8). An example
follows.
Key
stroke
|
Explanation
|
PACE
|
Loads executive program. The
screen output should look as Figure 6.2. This assumes that you have not yet
loaded the program. If the executive program is still in memory, then skip
this step and highlight the CONST.EXE program and press <enter>. The
Road Construction Menu should appear as shown in Figure 6.8.
|
R
|
Branches to load machine rates for
road construction calculations.
|
Key
stroke
|
Explanation
|
H
|
Switches to manual machine
selection mode. You can identify a maximum of 12 machine rates. Use the
cursor to highlight the desired machine rate file and press the space bar.
You will see a "#" sign appear to the left of the file name to
indicate it has been selected. Repeat until you have identified the 5 machine
rate files shown in Figure 6.9. Then, press <return> to begin loading
the files.
|
Alternatively, you could
automatically select the first 12 machine rate files on your data disk for
use as machine/labor combinations for road construction by pressing [A].
|
|
Next, select the road construction
activity you want to evaluate. Let's start with surveying.
|
|
1
|
Branches to the survey window.
This should appear as Figure 6.10.
|
200
|
Move the cursor to the
equipment/labor combination you want and enter the production rate. The
activity totals will appear in the lower box.
|
<esc>
|
Escape returns to the menu.
|
Alternatively, you can press <pg dn> or <pg up> to move
through the other construction activity screens.
|
|
Repeat this procedure for road
construction activities 2 through 7.
|
|
Skip any activities you do not
need.
|
|
At any time you can view the road
cost summary sheet by pressing <esc> to return to the menu and entering
(8).
|
|
An example of a summary screen is
in Figure 6.11. If you move the cursor to highlight any activity, the
equipment mix for that activity is indicated by arrows to the left of the
appropriate equipment/labor combinations in the lower window.
|
|
<esc>
|
Returns to the main menu.
|
Key
stroke
|
Explanation
|
7
|
Branches to the
landings menu (Figure 6.12). The results from this menu do not appear in the
road cost summary. The cost for landing construction however, will be used in
the UNIT.EXE program. It is saved along with the road costs when you select
the save mode.
|
<esc>
|
Returns to the main menu.
|
Key
stroke
|
Explanation
|
S
|
Selects the save
data mode. The save data mode has three purposes. First, it provides data for
Production and Unit Cost program (UNIT.EXE); second, it provides a way of
updating road cost estimates, and third, it is an easy way to create costs
for other road standards by modifying production rates in existing files.
|
Y
|
Indicates you want to continue with the save option. If
you do not want to do this, press <N>.
|
Low-std
|
File name under
which the data is to be saved.
|
6.5 Production and Unit Cost
Harvesting production and unit costs are
calculated in the UNIT.EXE program. An example of the UNIT.EXE program follows
using sample files from the disk.
Key
stroke
|
Explanation
|
PACE
|
Loads executive
program. The screen output should look as Figure 6.2. This assumes that you have
not yet loaded the program. If the executive program is still in memory, then
skip this step and select the UNIT.EXE program. (Figure 6.13)
|
Key
stroke
|
Explanation
|
R
|
Reads all machine
rates and road costs on the disk. A maximum number of 40 machine rates and 10
road standard files (.RCS) which can be considered at one time.
|
The machine rates to be used in calculating the felling,
yarding, loading, transport, and the road cost are now entered. This is done
in two steps: (1) use the tab key to highlight the harvesting activity and
(2) use the cursor control arrows to highlight the appropriate machine rate
or road construction rate and press <enter>. Select the machine rates
and road standard shown in Figure 6.14.
|
|
C
|
Press <C> when
you have completed selection of the machine files for the harvesting
activities and the road file for the road standard.
|
Key
stroke
|
Explanation
|
1
|
Selects the felling
production and cost window (Figure 6.15).
|
Note the machine costs already appear from the previous step.
Complete the information by using the cursor arrow to identify the
location, enter the data and then move the cursor to the
next data entry location.
|
Table 6.4 Falling and
Bucking Screen Formulas
Row
|
Description
|
1
|
Machine Cost (.MAC,
.AML, or .TRK file)
|
2
|
Machine minutes to fell and buck tree
|
3
|
Volume per tree
|
4
|
Delay time (minutes per hour that machine is working, but
not doing planned work)
|
5a
|
Felling and bucking
production per machine hour
|
5b
|
Ownership part of felling and bucking unit cost
|
5c
|
Operating part of
felling and bucking unit cost
|
5d
|
Labor part of felling and bucking unit cost
|
5e
|
Total unit cost for
felling and bucking
|
Rows (1) - (4) are
input data.
Row (5a) = Row (3) * [ 60 - Row (4) ] / Row (2) Row (5b) = Row (18)a / Row (5a) Row (5c) = Row (18)b / Row (5a) Row (5d) = Row (15)c / Row (5a) Row (5e) = Row (5b) + Row (5c) + Row (5d)
------------------
a Refers
to Row (18) of Table 6.1
b Refers to Row (18) of Table 6.2 c Refers to Row (15) of Table 6.3 |
Key
stroke
|
Explanation
|
The hourly
production adjusted for operating delays and unit costs are shown on the
lower screen.
|
|
<esc>
|
Returns to menu or you can move to the next screen by
using the <pg dn> key.
|
2
|
Complete the
skidding activity screen similarly using the test data in Figure 6.16.
|
The skidding production and costs will not appear until
after the road and landing data window has been completed because the road
spacing information is needed and is not available at this point.
|
Table 6.5 Skidding
Screen Formulas
Row
|
Description
|
1
|
Machine cost (.MAC,
.AML, or .TRK file)
|
2
|
Move-in time (machine time landing to landing)
|
3
|
Volume per cycle
(trip)
|
4
|
Outhaul velocity (empty)
|
5
|
Lateral outhaul
velocity
|
6
|
Hook time
|
7
|
Lateral inhaul
velocity
|
8
|
Inhaul velocity (loaded)
|
9
|
Unhook time
|
10
|
Delay time (machine time the equipment is involved in
working delays, i.e. meter is running)
|
11
|
Not applicable
|
12a
|
Skidding production per machine hour
|
12b
|
Ownership part of
skidding unit cost
|
12c
|
Operating part of skidding unit cost
|
12d
|
Labor part of
skidding unit cost
|
12e
|
Total unit cost for skidding
|
Rows (1) - (10) are
input data.
Row (12a)a = (Volume per landing) / (Trips × Effec Cycle Time / 60 + Move-in) Row (12b) = Row (18)b / Row (12a) Row (12c) = Row (18)c / Row (12a) Row (12d) = Row (15)d / Row (12a) Row (12e) = Row (12b) + Row (12c) + Row (12d)
------------------
a Volume
per landing calculated from information in the Roads / Landings screen. Trips
is equal to volume per landing divided by volume per trip.
b Refers
to Row (18) of Table 6.1
c Refers
to Row (18) of Table 6.2
d Refers
to Row (15) of Table 6.3
L-shaped Skidding
Pattern
If Row (5) and Row
(7) are not zero then calculations are for lateral skidding to a corridor,
and then skidding along the corridor to the landing
Cycle Time = [ K *
D1 / Row (4) + .25 * D2 / Row (5) + Row (6) + K * D1 / Row (7) + .25 * D2 /
Row (8) + Row (9) ] * W
where
K = 0.5 / Row (6)
from Table 6.8
D1 = Row (2) from Table 6.8 D2 = Row (3) from Table 6.8 W = Row (5) from Table 6.8
Radial Skidding
Pattern
If Row (5) and Row
(7) are zero then calculations are for radial skidding to a central landing.
The average skidding distance is approximately,
AYD = { .333 * SQR [
(F*D1) * (F*D1) + (D2) * (D2) ] + .333 * SQR [ (.5*F*D1) * (.5*F*D1) + (.5*D2)
* (.5*D2) ] } * W
where
F = 1.0 / Row (6)
from Table 6.8
D1 = Row (2) from Table 6.8 D2 = Row (3) from Table 6.8 W = Row (5) from Table 6.8
Cycle Time = AYD /
Row (4) + Row (6) + AYD / Row (8) + Row (9)
Effective Cycle Time
= Cycle Time × 60 / [60 - Row (10)]
|
Key
stroke
|
Explanation
|
If lateral inhaul
and lateral outhaul are left as zero the timber is assumed to be skidded to a
central landing by the shortest path. This can be adjusted by using a weave
factor in the Roads/Landing screen. Using the <pg dn> key, go to the
roads/landing screen to look at the data needed.
|
|
Complete the other screens shown in Figures 6.17 through
6.19.
|
Table 6.6 Loading Screen
Formulas
Row
|
Description
|
1
|
Machine cost (.MAC,
.AML, or .TRK file)
|
2
|
Machine minutes per cycle
|
3
|
Volume per grapple
(or other) load
|
4
|
Delay time (minutes per hour that machine is working, but
not loading, i.e. sorting)
|
5-6
|
Not applicable
|
7a
|
Loading production per machine hour
|
7b
|
Ownership part of
loading unit cost
|
7c
|
Operating part of loading unit cost
|
7d
|
Labor part of
loading unit cost
|
7e
|
Total unit cost for loading
|
Rows (1) - (4) are
input data.
Row (7a) = Row (3) * [ 60 - Row (4) ] / Row (2) Row (7b) = Row (18)a / Row (7a) Row (7c) = Row (18)b / Row (7a) Row (7d) = Row (15)c / Row (7a) Row (7e) = Row (7b) + Row (7c) + Row (7d)
------------------
a Refers
to Row (18) of Table 6.1
b Refers to Row (18) of Table 6.2 c Refers to Row (15) of Table 6.3 |
Key
stroke
|
Explanation
|
<esc>
|
Returns to the menu.
|
S
|
Selects the save mode if you want to keep the parameters
and results of this analysis.
|
Study-1
|
Creates a file
(Study-1 .UCD) for later recall using the (L) option.
|
Q
|
Quit. Returns to main menu.
|
<esc>
|
Leaves the PACE
program.
|
Table 6.7 Truck
Transport Screen Formulas
Row
|
Description
|
1
|
Truck cost (.TRK
file)
|
2
|
Distance (one way)
|
3
|
Volume per truck
load
|
4
|
Speed unloaded
|
5
|
Loading time
|
6
|
Speed loaded
|
7
|
Unloading time
|
8-10
|
Not applicable
|
11a
|
Truck transport per
machine hour
|
11b
|
Ownership part of truck transport unit cost
|
11c
|
Operating part of
truck transport unit cost
|
11d
|
Labor part of truck transport unit cost
|
11e
|
Total unit cost for
truck transport
|
Rows (1) - (7) are
input data.
Row (11a) = Row (3) * 60 / [Row (2) / Row (4) + Row (5) + Row (2) / Row (6) + Row (7) Row (11b) = Row (18)a / Row (11a) Row (11c) = Row (18)b { Row (3) * 60 / [Row (2) / Row (4) + Row (2) / Row (6) ] } Row (11d) = Row (15)c / Row (11a) Row (11e) = Row (11b) + Row (11e) + Row (11d)
------------------
a Refers
to Row (18) of Table 6.1
b Refers to Row (18) of Table 6.2 c Refers to Row (15) of Table 6.3 |
6.6 Sensitivity Analysis
The sensitivity of production and costs to
changes in the skidding or road cost variables can be examined at any time by
paging to the appropriate screen and changing the data. If the machine rate or
road standard is changed in this way, the percentage in ownership, operating,
and labor remains the same with the new rate. To change to a different machine
rate or road file, return to the menu <esc> and read the new machine rate
files (R). Then, use the cursor and tab keys as before. The UNIT.EXE program
will read the new cost files and your other data will still be available.
Remember to save your Unit Cost file before you exit the UNIT.EXE program.
Table 6.8 Roads/Landings
Screen Formulas
Row
|
Description
|
1
|
Road cost (.RCS
file)
|
2
|
Road spacing
|
3
|
Landing spacing
|
4
|
Harvest removal per unit area
|
5
|
Skidding weave
factor
|
6
|
One way or two way skidding factor
|
7
|
Cost per landing
|
8
|
Near optimal road spacing
|
9
|
Near optimal landing
spacing
|
10-14
|
Not applicable
|
15a
|
Not applicable
|
15b
|
Ownership part of road unit cost
|
15c
|
Operating part of
road unit cost
|
15d
|
Labor part of road unit cost
|
15e
|
Total unit cost for
roads/landings
|
Rows (1) - (7) are
input data.
Rows (8) and (9) are calculated using calculus and / or numerical approximation techniques beyond the scope of this manual. You can verify their goodness by substituting the values displayed in Row (8) and Row (9) into Row (2) and Row (3) and observing the change in TOTAL COST, Row (15e). Row (15b) = [ Row (1)a * Row (3) / 1000 + Row (7) ] / [ Row (4) * Row (2) * Row (3) / 10000 ] Row (15c) = [ Row (1)b * Row (3) / 1000 + Row (7) ] / [ Row (4) * Row (2) * Row (3) / 10000 ] Row (15d) = [ Row (1)c * Row (3) / 1000 + Row (7) ] / [ Row (4) * Row (2) * Row (3) / 10000 ] Row (15e) = Row (15b) + Row (15c) + Row (15d)
------------------
a Ownership
component of Row (1) from (.RCS) file.
b Operating component of Row (1) from (.RCS) file. c Labor component of Row (1) from (.RCS) file. |
The near optimal road and landing spacing is
shown on the Road/Landings screen (Figure 6.19). To find the cost associated
with this road and landing spacing, enter the road spacing and landing spacing
indicated. The results are shown in Figure 6.20. A reduction of $0.17 per cubic
meter is achieved by reducing the road spacing to 459 m and the landing spacing
to 250 meters. Although the road cost increases to $1.39 per cubic meter, the
reduced skidding cost more than compensates for this increase.
The UNIT.EXE program is not designed to have
zero landing spacing. A default value of 10 meters is used. If you want to
analyze continuous landings, the default value of 10 meters will not
appreciably increase the skidding distance or affect the unit costs.
6.7 Installing the PACE Program
The PACE program is designed to reside in a
directory of your hard disk. Create a subdirectory on your hard disk and copy
the PACE program disk contents into it. Also copy any example data files into
the same subdirectory as the PACE program.
When the PACE program loads data files or saves
data files, it will always do so to the subdirectory that the PACE program is
in. The Delete Utility on the PACE Master Menu can be used to erase files that
you no longer want.
No comments:
Post a Comment