Thursday, 2 November 2017

SITE LAYOUT FOR BUILDING


SITE LAYOUT SECTION



Section I BUILDING LAYOUT

OBJECTIVES:
The objectives of surveying for building construction are to lay out the proposed structure according to prepared plans and to mark the controlling points of the structure in the manner that is most useful to the construction forces. This marking consists of indicating the corners of the building and other horizontal and vertical positions by means of stakes, batter boards with string lines, drill holes, cut-and-fill notations, and similar conventional methods.

The actual layout of the building is usually preceded by some form of reconnaissance and location survey. The following procedures are typical of major building projects:
• Performing reconnaissance (aerial, map, and ground)
• Selecting site (paper and instrument).
• Establishing control (horizontal and vertical).
• Taking topography (plane table or transit stadia).

ORIENTATION
The building and its foundation are positioned according to the controlling dimensions and references appearing on prepared plans. The dimensions and references include the overall length and width of the structure, distances to road center lines and to other structures, measurements within the structure itself, and miscellaneous determinations concerning the approaches and rights-of-way.


LAYOUT OF A SIMPLE BUILDING
The plans for construction of a building give the location and elevation of the work relative to existing utilities and survey control marks. The dimensions of the building are part of the necessary data for establishing line and grade. Figure 6-1 illustrates atypical building layout using the following steps.

Establish baseline AB and locate CD by measurement
At point C, turn 90 degrees from B and locate corner stakes E and F by measurement.

Locate points H and G from point D in the same way
(1)
       (2)
Install batter boards.
(3)
Establish line and grade
     



BATTER BOARDS

The surveyor locates the corners of the building and determines the elevation of its foundation by carrying forward elevations from a benchmark, or other point of known elevation, to the foundation. To mark the general location, the surveyor sets stakes or slats. These will guide the initial excavation and rough grading. However, the stakes will be disturbed or destroyed during this work and somemore suitable marks must be placed to continue the construction. These suitable marks are called batter boards. The surveyor uses these temporary devices to mark the outline and grade of the structure and any special construction inside or outside.

Placement:
Batter boards of two 2- by 4-inch stakes driven into the ground and a crosspiece of 1- by 6-inch lumber naled to each stake. The surveyor drives the stakes about 3 to 4 feet away from the building line so they will not be disturbed by the construction but will be far enough apart to straddle the line to be marked. Note that in figure 6-2 only three stakes, one of them being a common post for two directions, are driven on outside corners. The length of the stakes is determined by the required grade line. They must be long enough to accept the 1- by 6-inch crosspiece to mark the grade. The surveyor cuts the 1- by 6-inch crosspiece long enough to join both stakes and nails it firmly to them after the grade has been established. The top of the crosspiece becomes the mark from which the grade will be measured.

Use of Instrument:
The surveyor sets all batter boards for one structure to the same grade or level line. An instrument is used to locate the building lines and mark them on the top edge of the crosspiece. A nail is driven at each of these marked points. A cord stretched over the top edge of two batter boards and held against the nails defines the building line and grade elevation.

Use of Cords:
Sometimes, an instrument is not available for marking the building line on the batter boards. If the corner stakes have not been disturbed, the surveyor can transfer the building line to the batter boards by stretching a cord over the batter boards and using plumb bobs held over the corner stakes. The surveyor moves the cord on each batter board until it just touches both plumb bob strings, marks the position of the cords, and drives in the nails.

Procedures:
The surveyor sets and marks the batter boards as follows:
After the corner stakes are laid out, drive
(1) 2- by 4-inch stakes 3 to 4 feet outside of each corner. These are selected to bring all crosspieces to the same elevation.
(2) The surveyor marks these stakes at the grade of the top of the foundation or at some whole number of inches or feet above or below the top of the foundation. Use a level to mark the same grade or elevation on all stakes.
(3) Nail 1- by 6-inch boards to the stakes to the top edge of the boards and flush with the grade marks. Mark the distance in crayon on these boards.
(4) Locate the prolongation of the building lines on the batter boards by using an instrument or a line and plumb bob
(5) Drive nails into the top edges of the batter boards to mark the building line




INTERIOR TRANSFER OF LINE AND GRADE
Occasionally, it is necessary to transfer lines and grades from outside to inside a building and to the upper stories for establishing wall faces, floor levels, and columns or for setting machinery precisely. The surveyor does this by traversing and leveling.

Location:
The surveyor locates instrument stations outside of the building to establish a line that, when extended, will intersect the building at a window or doorway. The instrument is set on the station farthest from the building and sighted on the point nearest the building. The surveyor transfers the line to the building by sighting the instrument on a plumb bob held in an upper-story window.
From this point, the line is extended in any direction inside the building by setting up on the point and using the outside stations as a back sight. The line is prolonged by double centering. Because of the short sights used, the surveyor may accurately set an angle that is to be turned to clear an obstruction and then measure by repetition.

Direct Leveling:
To transfer vertical control into a building, the surveyor uses direct leveling, if possible. For elevation transfer to an upper story, a steel tape is suspended with a weight attached to the lower or zero ends. To insure accuracy, the weight should approximately equal the normal tension of the fully supported tape minus one half of the weight of the suspended portion of the tape. A level is set up on the first floor, and a reading is taken on the suspended tape.
Another reading is taken on the tape with a level set on the upper floor. This gives data from which the HI of the instrument on the upper floor is computed. A rod is now held on some point on the upper floor to be used as a benchmark and its elevation determined. The surveyor may also establish elevations on the second floor by using the rod upside down (often called an inverted rod) and marking the elevation on a wall.


Section II. UTILITIES LAYOUT

DRAINAGE:
Utilities drainage refers to the sewer systems for surface water and liquid waste. The design and location of a drainage or storm sewer system will depend upon the size and topography of the area to be drained, the intensity of rainfall expected, the runoff characteristics of the area, and the location of the disposal point. The area to be drained includes the installation and any area around it that will drain into the installation. The intensity of the rainfall in inches per hour is based on records of past storms. The runoff characteristics are determined by the type of soil and ground cover.


DESIGN AND LOCATION:
Using the factors mentioned and the best available topographic map of the area, the surveyor designs and locates the sewer lines on paper. Once the paper location is accomplished, the centerline of the ditch is staked and profile levels run. The profile and grade lines are plotted and cut stakes set.
After the trench is dug, batter boards are set for the alignment of pipes and placement of manholes or drop inlets. The surveyor usually places batter boards for sewer alignment at intervals of 10 to 25 feet and sets them on edge across the trench (figure 6-3). Then the surveyor determines the interval between batter boards, the station number, and the elevation of the sewer grade at each batter board.
The term sewer grade is interchangeable with such other terms as invert grade, pipe grade, flow line, and grade line elevation. They all mean the same thing, the elevation of the low point on the inside circumference of the pipe. All sewer lines are designed with this elevation as the controlling factor. The surveyor must set all grade marks on the batter boards between two successive manholes at the same distance above the invert grade.

Battens:
The surveyor nails battens (small pieces of wood) to the batter boards to indicate sewer alignment. All battens are set vertically on the same side of the batter boards, with the same edges directly over the center line of the sewer. As work progresses, the surveyor must check the alignment of these battens frequently. This is done by sighting past the edges marking the center line. Any batten that has been moved or disturbed will be visible immediately.

Sighting Cords:
The surveyor uses a sighting cord stretched parallel to the center line of the sewer at a uniform distance above the invert grade to transfer line and grade into the trench. After computing the invert elevation, the surveyor adds an even number of feet to establish the elevation of the cord at each batter board. This position is marked on the center line edge of each batten by a nail. The sighting cord is fastened to the battens at these nails and this establishes the alignment of the sewer. The center line is directly below the cord, and the sewer invert grade is at the selected distance below the cord.




Grade Transfer:
To transfer the grade, usually in feet or feet and inches, from the sighting cord to the pipe, the surveyor uses a rod or stick called a grade pole, with a mark at a distance from the foot piece equal to the distance between the sighting cord and the invert grade (figure 63). The foot piece is placed on the invert of the pipe, and the rod plumb is held. The pipe end is then raised or lowered until the mark on the grade pole is on a horizontal line with the cord. A plumb line is held lightly against the cord and the pipe shifted sideways until its crown is directly below the point of the plumb bob. The grade pole is again placed in position, held plumb, and its mark checked against the cord.


THANKS!





Tuesday, 31 October 2017

Quantity Survey Definition and Methods


Quantity Survey


Modern quantity surveyors provide services that cover all aspects of procurement, contractual and project cost management. They can either work as consultants or they can be employed by a contractor or sub-contractor.
The main role of Quantity Surveyors is to estimate the building cost. Each building can be divided into different parts, cost of each part can be estimated and by adding cost of all parts of building together will give contractors an estimated cost for the whole work. It's been proved in practice that by adding cost of quantities, material used for project and labour will provide us with the total cost of the project. We must not forget that the bill provided by quantity surveyor is an estimate and it is prepared before any work starts to give a contractor estimated cost. Contractor then agrees to do the work based on the estimated cost that represents the proposed work.
Position of Quantity surveyor came available after builders realized how much work it requires to do all the measurements and calculations and it would be much more cost effective for them all to employ one person to do it. As soon as they implement this in practice architects and employers soon realized the effectiveness of quantity surveyors.
As we've already learned above the estimated cost of construction work prepared by quantity surveyor is used for tendering. Each builder can therefore price the work that needs to be done based on same bill of quantities and this is what gives building industry a healthy competition.

Every good quantity surveyor must have a good knowledge of building materials and construction. Surveyor must be very systematic and careful to provide correct calculations as well as be able to visualize drawings and details. To make sure that the quantity bill is accurate, surveyor needs to be sure of all requirements of architects. Arranged bill needs to be clear and easily understood to prevent any costly misunderstandings.

There is basically two method's

1) Rough cost estimate  


2) Detailed cost estimate
   


Requirements for Estimation:-


1) Drawings, i.e Plans, elevation, sections etc.


2) Specifications.


3) Rates.


1) Rough Cost estimate :-

A Rough cost estimate is the approximation of the cost of a program, project, or operation. The Rough cost estimate is the product of the cost estimating process. The Rough  cost estimate has a single total value and may have identifiable component values.


2) Detailed cost Estimate:-


The preparation of detailed estimate consists of working out quantities of various items of work and then determines the cost of each item. This is prepared in two stages.

I) DETAILS OF MEASUREMENTS AND 

                                     CALCULATION OF QUANTITIES.

The complete work is divided into various items of work such as earth work concreting, brick work, R.C.C. Plastering etc., The details of measurements are taken from drawings and entered in respective columns of prescribed preformed. The quantities are calculated by multiplying the values that are in numbers column to Depth column as shown below:
 Details of measurements form


In detailed estimate :-

           1) Long and Short Wall Method
2) Centre Line Method
3) Partly centre line & partly cross wall method.
4) Graphical Method


1). Long & Short Wall Method:-

In this method, the wall along the length of room is considered to be long wall while the wall perpendicular to long wall is said to be short wall. To get the length of long wall or short wall, calculate first the centre line lengths of individual walls. Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its centre line length. Thus the length of short wall Measured into in and may be found by deducting half breadth from its centre line length at each end. The length of long wall usually decreases from earth work to brick work in super structure while the short wall increases. These lengths are multiplied by breadth and depth to get quantities.

2) Centre Line Method:-

This method is suitable for walls of similar cross sections. Here the total centre line length is multiplied by breadth and depth of respective item to get the total quantity at a time. When cross walls or partitions or verandah walls join with main all, the centre line length gets reduced by half of breadth for each junction. Such junction or joints are studied carefully while calculating total centre line length. The estimates prepared by this method are most accurate and quick.

3)  Partly centre line & partly cross wall method:-

This method is adopted when external (i.e., around the building) wall iSOFT one thickness and the internal walls having different thicknesses. In such cases, centre line method is applied to external walls and long wall-short wall method issued to internal walls. This method suits for different thicknesses walls and different level of foundations. Because of this reason, all Engineering departments are practicing this method.

4) Graphical Method:-

Graphical method is mostly use for Cutting and Filling in Road and Cannel project’s.
In this method we use Grap paper  for finding cutting and filling.
Thanks!

Watch Video Tutorial


(video is preparing) !!!

Monday, 30 October 2017

How to Find Retaining Wall Part's


Retaining Wall:-

retaining wall is a structure designed and constructed to resist the lateral pressure of soil, when there is a desired change in ground elevation that exceeds the angle of repose of the soil, is called Retaining wall.



Retaining Wall Part's:-

1)Top
2)Bottom
3)Slope
4)Height

Method:-

1)Top = Height * Slope - Bottom
2)Bottom = Height * Slope + Top
3)Slope = Bottom – Top / Height
4)Height = Bottom – Top / Slope











Watch Video Tutorial


Example:-

1)Slope = 1.25 – 0.80 / 3.50 = 0.128
2)Top = 3.50 * 0.128 – 1.25 = 0.802
3)Bottom = 3.50 * 0.128 + 0.80 = 1.249
4)Height = 1.25 – 0.80 / 0.128 = 3.51


Wednesday, 25 October 2017

How to find length & width for slab if thickness and volume is given?




 How to find length & width for slab if thickness and volume is given? 


Given data:-
Concrete Volume in Slab = 1500 cft
Thickness of Slab            = 5"

Now finding The length and width of slab

Solution:-

When 
            length = Width = ?
L * B * H = 1500 cft
L * B * 5/12 = 1500 cft  (Divide 5 inches by 12 to become ft)

When

Length = width    So,
L * L * 5/12 = 1500 cft
(L)2* 5/12 = 1500
(L)2* 5/12 = 1500 * 12
5L/5 = 18000/5

Now taking Under-root ( Under-root = ;;}

{(L)2};; =  { 3600};;

 L = 60'
 B = 60 ' 



Sunday, 22 October 2017

CONVERSATION FACTORY


Conversation Factory 

1 Acre = 4046.86 Sq meter
1 Acre = 4840 Sq yard
1 Acre = 43560 Sq feet
1 Yard = 36 inch
1 Yard = 3 feet
1 Yard = 0.983612 or 1 meter
1 Sq Yard = 0.83612 Sq meter
1 Sq Yard = 9 Sq Feet
1Sq yard = 1296 Sq inch

1 meter = 39.37 inch
1 meter = 3.28 Feet
1 Sq meter = 10.763 Sq Feet
1 Feet = 0.304 meter
1 Feet = 12 inch
1 Sq Feet = 011 Sq yard
 1 Sq feet = 144 Sq inch
1 inch = 2.54 cm
1 inch = 0.0254 meter
1 inch = 0.0277 yard
1 inch = 0.0833 feet

1 Sq inch = 0.00064516 Sq meter
 1 Sq inch = 0.00077160 Sq yard
1 Sq inch = 0.00694444 Sq feet


Saturday, 21 October 2017

WHAT IS SURVEYING AND SURVEY CATEGORIES?


SURVEYING AND SURVEY CATEGORIES


Definition:-
In general, surveying is performed to determine the relative location or positioning of points on or near the earth's surface.  More specifically, surveying is the science of making measurements, relative to known or assumed datum’s and standards, and applying the principles of mathematics to such measurements to determine existing or future horizontal and vertical position, from area, magnitude, boundaries, and extent of land parcels and topographical features.

Survey categories:-

1. Geodetic Surveys - Surveys, which establish control networks on a mathematical datum so that measurements will reflect the curved (ellipsoidal) shape of the earth.

 Read ↠↠↠↠  METHODS OF LEVELING

 2. Land Surveys - Surveys which include retracement of existing land ownership boundaries or the creation of new boundaries.



3. Engineering Surveys - Surveys performed for the location, design, construction, maintenance and operation of engineering projects.




4. Construction Surveys - Surveys which establish stakes in the ground, and other like reference points, at known horizontal and vertical positions to define location and size of each component of the facility to be constructed, enable inspection of contract items, and serve as a basis of payment for work.




5. Cartographic Surveys - Map making from original survey is called Cartographic survey.





Thanks!